Civic Link - Block 3

Latest News

  • April 2026

    Construction of Civic Link Block 3 will take place in two (2) stages:

    • Stage 1 Phillip Street works is planned to begin in May 2026 and continue to October 2026*.
    • Stage 2 Horwood Place works will begin once stage 1 is complete, forecast for October 2026, and continue until December 2027 *.
    • *Weather and site conditions permitting.

    All footpaths and businesses in Horwood Place will remain open and accessible during Stage 1. Outdoor dining will be open in Stage 1. However, during Stage 2 (expected to begin in October 2026) outdoor dining licenses will be suspended. Council’s contractors will prepare a detailed staging plan for the construction program that will guide the suspension dates for outdoor dining. Council will work closely with businesses and provide more information as soon as possible.