George Street East Pedestrian & Cyclist Paths

Latest News

Latest News

  • April 2026 - Construction Update

    The project is entering its final stage, with electrical works nearing completion and construction of the Noller Parade bike path due to commence shortly. The project is tracking for completion in June 2026.
  • February 2026 - Construction Update

    Due to unfavourable ground conditions encountered in late 2025, further geotechnical investigation and deeper excavation were required to be undertaken to inform the redesign of light pole footing. The project completion is now expected in May 2026.
  • March 2025 - Construction Update

    The new pathways between Eleanor Street and Clay Cliff Creek are now open. Construction on the final section between Clay Cliff Creek and George Street (Stage 2B) is scheduled to begin in the coming months, with completion expected in late 2025.