George Street East Pedestrian & Cyclist Paths

Latest News

  • February 2026 - Construction Update

    Due to unfavourable ground conditions encountered in late 2025, further geotechnical investigation and deeper excavation were required to be undertaken to inform the redesign of light pole footing. The extended heritage approval process required for these onsite investigations has had significant impact on the project schedule.

    The construction program was thus extended to accommodate the heritage approval, additional investigations, redesign and construction timeline required for a total of 26 new light pole footings.

    These investigations works were completed in late January 2026 and the revised design has been finalised. The project completion is now expected in May 2026.